Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Two of Chemainus photographer Marston’s images picked among National Geographic’s 2018 elite

Rare double honour from the 36 best Your Shots out of nearly 19,000 photos

Police officer recounts wild car chase through downtown Ladysmith and Duncan

B.C. Supreme Court trial of Armaan Singh Chandi hears of pursuit following Nanaimo drive-by shooting

Ladysmith a stride closer to fitness trail

Work could get underway on initial groundwork this spring

Small external fire extinguished quickly at Catalyst’s Crofton pulp mill

Fire department called Monday afternoon as part of protocol, but services not needed

B.C. storm totals $37M in insured damages

The December storm wreaked havoc on B.C.’s south coast

Fashion Fridays: Inspirational gym outfits

Kim XO, helps to keep you looking good on Fashion Fridays on the Black Press Media Network

Overworked and understaffed: More than 300 vacancies in Vancouver Island nursing

Tentative deal with province includes ‘working short premium’ to encourage hiring

Minor mattress fire could have killed, Nanaimo Fire Rescue warns

Public fire safety warnings issued following potentially deadly fire on Victoria Road

Investigators await forensics in fatal Mill Bay police shooting

Indepedent investigation continues after Chris Bloomfield killed in Mill Bay in November

Russian fighter jets collide over Sea of Japan crews eject

One plane crashed after its crew ejected safely, the other crew also ejected but they have not been found

Judge to deliver verdict in British sailor’s gang rape case

The alleged gang rape took place at a Halifax-area military base in 2015

Campbell River resident asking for bottles and cans to help Chemainus stabbing victim

Janelle Guyatt suffered serious injuries during a May 2016 knife attack

B.C. minister fears money laundering involves billions of dollars, cites reports

The government had estimated that it was a $200-million a year operation, instead estimates now peg the problem at $1 billion annually

BC Hydro scammers bilked customers out of nearly $45,000 in 2018

Nearly 2,000 people reported scams to the utility, as they continue to be more common

Most Read